PAL Jaya Completes Seven Main Pipes Construction Packages in Zero Zone

PD. PAL Jaya now has finished constructing 7 of total 9 main pipes construction packages in zero zone.

Two other packages are still in progress. Those are located on Jalan Asia Afrika and Jalan Sudirman Timur

PD. PAL Jaya President Director, Subekti explained, those seven pipes construction packages are located on the south and north sides of Jalan Gatot Subroto,  continuation of the north side, Jalan Senopati, on the road in front of Panin Bank Building, Jalan Patra, and Jalan Denpasar.

"Two other packages are still in progress. Those are located on Jalan Asia Afrika and Jalan Sudirman Timur," he added, Wednesday (11/27).

PD. PAL Builds Centralized Sewage Piping Network on Jalan Gatot Subroto

According to him, those two packages had stopped temporarily due to Asian Games, Asian Para Games, MRT Jakarta development, and sidewalk revitalization.

"We are targeting those construction packages to finish in 2020," he mentioned.

Linked News
Popular News indeks
  1. Jakarta and Lampung Collaborate to Launch Lampung-in App

    access_time15-06-2025 remove_red_eye461 personDessy Suciati
  2. City Council Fractions Deliver General Views on 2024 APBD Accountability

    access_time16-06-2025 remove_red_eye367 personFakhrizal Fakhri
  3. Cloudy Morning, Rainy Afternoon this Tuesday, BMKG Says

    access_time17-06-2025 remove_red_eye303 personDessy Suciati
  4. Jakarta Fair Kemayoran Begins, Hailing City’s 498th Anniversary

    access_time20-06-2025 remove_red_eye284 personDessy Suciati
  5. Here are Parking Spaces around Lapangan Banteng for Jakarta's Anniversary

    access_time21-06-2025 remove_red_eye227 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik